Delhi Construction Curbs This Winter: Dates, GRAP and What Homebuyers Should Know
Delhi restricts dust-generating construction from 1 November 2026, with a complete construction and demolition ban planned from 10 December 2026 to 20 January 2027. Here is what is restricted and what it could mean for under-construction homes.
SSite Admin · · 5 views

Construction across Delhi is slowing down for winter. The Delhi government's winter action plan and orders from the Commission for Air Quality Management (CAQM) together restrict building work for the next few months.
The key dates
- 1 November 2026 to 31 January 2027: Dust-generating demolition and outdoor civil construction are restricted in Delhi under the government's winter plan.
- 10 December 2026 to 20 January 2027: A complete ban on construction and demolition in Delhi, as announced by Chief Minister Rekha Gupta.
- 5 to 20 November 2026: CAQM separately restricted dust-generating construction and demolition across the NCR, along with 50% office attendance.
Construction sites larger than 500 sq m are being monitored through Delhi's dust portal and AI-enabled cameras.
GRAP status
The Graded Response Action Plan (GRAP) adds curbs as air quality worsens. Stage II was invoked on 2 November and Stage III on 6 November 2026. Around 18 November, CAQM said reports of Stage IV being imposed were incorrect and that Stage III remained in force. GRAP stages can change quickly, so check the latest CAQM order.
What is exempt
CAQM's 5–20 November order exempted railway, Metro, airport, inter-state bus terminal (ISBT), hospital and other projects of national importance. Reports describe the 10 December to 20 January ban as having no exceptions; check the official order for the final position.
What it means for homebuyers
- Under-construction projects in Delhi could lose several weeks of work this winter. If you have booked a home, ask your builder how they plan for the ban and whether the delivery date changes.
- Check your agreement and RERA filings. Note the possession date declared to RERA and what your agreement says about delays caused by government orders.
- Ready-to-move homes are not affected. Many buyers find them more appealing in winter for this reason. See ready-to-move vs under-construction homes.
- Home renovation and repair work that creates dust may also be restricted during the ban.
Sources: Outlook India (28 September 2026); Dynamite News (21 August 2026); All India Radio news (31 October and 6 November 2026). This article is general information; follow official orders.